Scaling tech across sites: the standardisation paradox


Key takeaways
Why do multi-site rollouts stall after a successful pilot?
You can design the right technology solution. You can nail the requirements, value engineer it ruthlessly, and run a flawless proof of value. And then the real project begins: rolling out across multiple sites, where every plant director believes their operation is unique.
The mythology around “global rollouts” says that selecting the right technology is the key challenge. In practice, choosing the technology is often the easy part. The greater challenge is convincing multiple sites to adopt a common way of working while preserving enough local autonomy for each operation to remain effective.
The pattern is consistent. Corporate teams push for standardisation to maximise value and reduce complexity. Local sites push for flexibility to reflect their operational realities. Both positions are valid. The conflict only arises when organisations assume they have to choose one or the other.
Should the first site be a template or a laboratory?
The common approach is to try to solve global standardisation before value has been proven. That produces workshops, discussions and documents, with very little tangible outcome.
The better approach is to treat the first site as a laboratory. Not a pilot, and not yet a template. A laboratory exists to prove five things:
Only when those five are answered should the conversation turn to scale. Start small. Think enterprise.
Fazer took this route. They resisted the pull towards immediate global rollout and validated the MES platform in a controlled environment at their Vantaa site first, building confidence before scaling investment and proving operational value before discussing enterprise value. Structured discovery produced clear requirements, clear success criteria and controlled scope, which in turn produced better stakeholder alignment and fewer surprises when delivery moved to their Lahti location.
The honest part: discovery took longer than expected. Not because the process was complicated, but because sites had different interpretations of the same process.
Why do sites disagree when they are running the same process?
Because they are not describing it the same way.
Different definitions of OEE. Different interpretations of what counts as downtime. Different production reporting practices. On the surface these look like integration problems. They are not. Integration is rarely the blocker. Vocabulary is.
And a vocabulary gap is really a business architecture gap. If two plants cannot agree what a stop is, no amount of middleware will make their numbers comparable.
Is a greenfield site easier to standardise than a brownfield site?
Conventional thinking says yes. Brownfield sites carry legacy systems, established processes and entrenched ways of working. Greenfield sites offer a clean slate, so standardisation should be simpler.
In reality, the challenge does not disappear. It moves. Instead of replacing existing systems, you are aligning stakeholder understanding, and that turns out to be just as difficult.
Brownfield sites expose legacy constraints. Greenfield sites expose alignment gaps. Both reveal the same underlying issue: no agreement on the business architecture.
In our experience the greenfield site is where enterprise standards get tested hardest, because it forces the organisation to answer questions it has never previously agreed at enterprise level.
What must be standardised, and what must stay local?
This is the paradox at the centre of every multi-site programme, and it has a workable answer.
Standardise what protects the business case. The platform, the data architecture, and the core process logic. Without these, comparison between sites becomes impossible, analytics lose their value, support costs escalate and the ROI quietly disappears.
Leave local what protects operational performance:
Training. Different operator profiles, shift structures and workforce characteristics.
The learning from Fazer so far is that standardisation succeeds where it visibly strengthens operations, and meets resistance where it feels like control. People defend what protects them. They resist what controls them.
How do you govern the difference?
The most successful global programmes do not create more governance. They create clearer governance. Clear escalation routes achieve more than additional meetings.
Without a defined escalation path, every issue gets renegotiated and every decision becomes political. With one, decisions happen faster, expectations are clear and accountability improves.
A simple way to make this explicit is a RAG decision rights model:
Rad decision model
| Zone | Label | Who decides | Contents |
|---|---|---|---|
| Red | Defend the core | Corporate | MES platform, data model, KPI definitions (OEE, downtime), cyber security standards |
| Amber | Negotiate the middle | Joint | Deployment sequence, functional prioritisation, reporting enhancements, process harmonisation |
| Green | Flex the edges | Site | Training plans, change champions, adoption strategy, local CI initiatives |
The practical value is that a disagreement stops being an argument and becomes a classification exercise: which zone does this sit in, and therefore who decides?
What goes wrong?
Three failure modes come up repeatedly.
Customisation addiction. It always starts with “we only need one small site-specific change”. Enough of those and the enterprise programme is gone: rework, lost time, damaged morale, and eroded board confidence. We saw this beginning at Fazer Vantaa site and advised pausing customisations for later review rather than absorbing them into scope.
Governance by committee. Multiple reviews, no decisions. The organisation feels collaborative while the programme stops moving. Consult widely, decide quickly.
The human problem, which is discussed least. Plant directors have often built successful operations through exactly the local optimisation you are now asking them to give up. When that is not acknowledged, it drives more resistance than any technical limitation ever will. Resistance is frequently not opposition. It is closer to grief. People are being asked to hand over systems they built and processes they own. Treat that as a technical problem and the programme will fail.
Where does this leave the business case?
For the enterprise, a single platform across multiple sites de-risks the investment story.
For operations, the formula is not “follow the template”. It is “protect the standard, improve the operation”. Sites that adopt the core standards and customise smartly outperform both the rigid and the rebellious.
For the commercial forecast, phased site-by-site measurement means the rollout no longer depends on every site delivering identical results. Benefits get measured locally, maturity differences are understood, forecasts reflect operational reality, and the overall business case stays intact. That gives executives confidence and operators realism at the same time.
Where should you start?
The playbook most transformations are missing
You need to be able to say, with confidence: “We are standardising on this because the business case depends on it. You have flexibility here because operational excellence depends on your expertise. And here is how we will make that distinction together.”
That credibility, having genuinely thought through what is non-negotiable versus what is negotiable, is what lets you defend a rollout to corporate leadership and local plant teams at the same time.
Identify your core. Identify your edges. Govern them differently.
Frequently asked questions
What should be standardised in a multi-site MES rollout?
Standardise what protects the business case: the platform itself, the data architecture, the core process logic and KPI definitions such as OEE and downtime. Without these, cross-site comparison is impossible, analytics lose value and support costs escalate. Everything else is a candidate for local ownership.
What should sites be allowed to control?
Deployment pace, change management approach, local functional priorities and training. These reflect differences in maturity, culture, workforce and shift structure. Standardising them rarely protects the business case and usually generates resistance, because sites experience it as control rather than support.
Why do multi-site technology rollouts fail?
Most fail on governance rather than technology: unclear decision rights, no escalation path, and accumulated site-specific customisation. A successful proof of value at one site does not transfer automatically, because the second site brings different definitions, different maturity and different leadership.
Are greenfield sites easier to standardise than brownfield sites?
No. Brownfield sites expose legacy constraints. Greenfield sites expose alignment gaps, because there is no existing practice to fall back on and the organisation must finally agree standards it has never formally defined. Both reveal the same issue: a lack of agreed business architecture.
How do you resolve standardisation disputes between corporate and site teams?
Classify the decision before debating it. A RAG model assigns each item to corporate ownership (red), joint governance (amber) or site ownership (green). Disputes then become a classification exercise with a defined escalation route, rather than a repeated negotiation.
Find Us
We have sites across the UK and North America
ITI Operations Limited
+44 (0) 1246 437600
enquiries@itigroup.com
Rotherside Road,
Sheffield,
South Yorkshire, S21 4HL
ITI Group Inc
33 Bloor St East 5th Floor,
Toronto,
Canada,
M4W 3H1
Get in Touch
"*" indicates required fields